Heavy rain poured last night before the roof was finished. No work was done due to the heavy rain.

Monthly Archives: September 2015
Under roof now.
Working on the roof.
Monday. Started to working on the roof. It will rain so hopefully the roof can be up ASAP. At the end of the day, most part of the roof is up but the middle still not completely covered.
Dawn sent an email to update the status.
Hi Helen, trusses were delivered Friday and being set today. Then plywood, paper and shingles to follow. These materials are made to withstand the elements so nothing to worry about there. Thx, Dawn
Foundation Stage (Approximately 30 Business Days) Apply for utilities now (water/sewer, power & gas)
· Excavation
· Foundation Footing Formed & Poured
· Foundation Walls Formed & Poured Sewer determination to be made (hung vs gravity)
· Water-proofing/Drain Tile/ Backfill/Plumbing Ground Works
· Basement & Garage Slabs Poured Construction entrance will need to be extended to garage slab
FOUNDATION WALK 9/17/15
Frame Stage (Approximately 30 Business Days)
· Floor Joists and Sub-flooring
· Wall Framing and Roof Shingles
· Windows & Exterior Doors
· Stairs
FRAME WALK Bring meter base & place add’l purchased items (MM/outlets/lights/etc.) as well as island
Started to install trusses.
Trusses are delivered.
More First floor framing work.
First floor framing
End of day of Thursday.
Foundation walk and started Frame work.
Foundation walk scheduled on Wednesday 9/15/15.
Dawn emailed us and said “Dennis just informed me we ran into a snag and he would now like to do the foundation walk on Wed at 9am.”