Cabinet walk is today. Jin and Vince met in the new house. Dawn sent email as following.
Drywall & Trim Stage (Approximately 30 Business Days)*supply propane for temp heat if necessary*
- Drywall hung, taped and finished
- Interior Trim, Paint Interior
- Flooring
- Kitchen Cabinets 37 calendar days to the ProHome Orientation walk (if all utilities completed)
- Countertops and Vanities
- CABINET WALK
Final Stage (Approximately 30 Business Days)
- HVAC, Electrical, & Plumbing Fixtures
- Appliances Installed
- Complete Painting & Touch-up
- Carpet
- Cleaning
- Final Grade (35’ around house)
PRO-HOME ORIENTATION WALK 5 business days to your NDI settlement
NDI Settlement Must have Occupancy permit at least 24 hours prior to settlement