Monthly Archives: September 2015
plumbing permit & status
Dawn sent an email regarding the permit and status.
Hi Helen, the plumber has pulled the permit and NDI paid on your behalf so when you receive the invoice, you can just mail the check to NDI. Each phase of construction is approximately 30 business days. Your construction package was released to the field on 8/17. Footers & walls have been poured as well as drain tile & waterproofing. Today the site is being backfilled with the plumber to start with the plumbing grounds works tomorrow afternoon. If Mother Nature cooperates and all goes well, we are probably looking at doing the foundation walk by the end of next week. Thx, Dawn
Foundation Stage (Approximately 30 Business Days) NDI will need assistance w/applying for utilities
· Excavation
· Foundation Footing Formed & Poured
· Foundation Walls Formed & Poured
· Water-proofing/Drain Tile/ Backfill/Plumbing Ground Works
· Basement & Garage Slabs Poured
FOUNDATION WALK