Q: I remember Dennis mentioned that the front porch step concrete pouring would happen last week. The weather is getting cold. I just checked the weather. We wouldn’t have another frozen weather in next few days. Hope the concrete can be poured soon, so the cold weather won’t damage the wet concrete.
A: Waiting on front door to be delivered & installed, then stoop will be poured
Q: Also, how is the progress of the electricity installation? Do we need to do anything to call electricity company? We already got the 400A meter base. Hope the after frame stage can be as fast as well. With the Thanksgiving in November and Christmas in December. We hope we can get things done as early as possible.
A: Once the meter base has been inspected by the county, I’ll notify you to contact Dominion to inform them of such
Q: We already contact the Propane company. What is the detail requirement of propane? 100 gallons?
A: Yes 100 gallon tank – I’ll let you know when to schedule delivery
Q: I also heard from a friend in construction business to warn me that don’t put on carpet and hardwood floor if the polywood still contains some moisture. Many new building’s polywood got wet in rain and some moisture still kept in polywood, and then the hardwood and carpet were put on. The floor would have problem within 2 – 3 years. Hope the propane can dry the polywood as well.
A: Flooring contractor measures humidity before hardwood installation as they are the ones that have to warranty it – they wouldn’t install it if it was going to affect the hardwood/warranty
Q: Also, would you please provide us some recommendation about the drive way contractors and grass sod contractors?
A: Concrete:
Builders Choice Concrete (540) 891-0900
Super Concrete (703) 368-9171
Asphalt:
Tibbs Paving (703) 330-1789
Landscaping:
Total Lawn (703) 928-2512
Green Sun (703) 926-5086